50-ACRE ASH POND CLOSURE
PROJECT SCOPE
The landfill was Capped with an 18” impervious clay liner and a 6” vegetative cover layer. Designed to control the stormwater were 7500 linear feet of diversion berms, 1900’ of HDPE down drains, energy dissipating Rip Rap features, and topped with matting and grassing.
The top of the landfill was prepared with a 12” crushed stone surface for future solar panel arrays along with an integral grounding system and rigid conduits for ease of wiring for the solar project.